Here's What's Happening:
Plumbing and Electrical Rough-in on main building
Plumbing Rough-in for Kitchen
Masonry ongoing on the lower level
Continuing Steel Deliveries and Installation
Install bar joists, bridging and decking on roof
Fire Proofing continues
Duct Delivery
Install Decking on Upper Level