Construction Pictures 2-3-2020
02/03/2020
Phase I Completion – July 31, 2019; Sitework & Utility Relocation
Phase II Completion – June 8, 2020; Classroom/Administrative/Cafeteria
Phase III Completion – July 29, 2020; Demolition of existing school/Front Parking Lot
Phase IV Completion – December 1, 2020; Gymnasium/Choral Rooms/Bus Drop-Off Lot
Here's What's Happening:
Plumbing and Electrical Rough-in on main building
Plumbing Rough-in for Kitchen
Masonry ongoing on the lower level
Continuing Steel Deliveries and Installation
Install bar joists, bridging and decking on roof
Fire Proofing continues
Duct Delivery
Install Decking on Upper Level
Coming Up:
Waterproofing of the foundation continues
Backfilling continuing
Fine grade and stone, bug spray!
Crane in place to erect steel beams!!!
What's happening this week and next: